4. Mandatory lubrication
Frequently check the level and quality of lubricating oil, hydraulic oil, coolant, brake fluid and fuel oil (water) of the concrete pump, and pay attention to the sealing of the whole machine. If the oil or water is insufficient or excessive during the inspection, the cause should be analyzed. At the same time, the lubrication of each lubrication point should be strengthened. It is recommended to add grease to the lubrication points every shift during the running-in period (except for special requirements). 5. Check parts
Keep the concrete pump clean, adjust and tighten the loose parts in time to prevent the wear of the parts from being aggravated or the parts from being lost due to looseness.
6. Mandatory maintenance
After the running-in period, the concrete pump should be subjected to mandatory maintenance, and the inspection and adjustment work should be done well, and the oil replacement should be paid attention to.