4. Only those who have received professional technical training and passed the examination can operate, use and maintain this equipment.
5. Due to the heavy weight of the jetting machine, it is required to place it on a firm ground, so that the jetting machine can be positioned reliably and in a horizontal state, and ensure that the outriggers of the vehicle are fully equipped before starting the manipulator or concrete pump, or pouring the sprayed material into the hopper. Extends out to prevent tipping.
6. The concrete sprayer should have a power cord at least 50 meters long, the voltage and frequency used are in compliance with the regulations, and the phase sequence is determined.
7. When the running distance is long, the manipulator should be turned to the transport position, and the big arm should be supported by the support.