Precautions for the use of the concrete placing boom machine Strictly abide by the rules of use. Correct operation is the guarantee to prevent accidents and extend the service life. A preparation before arrangement
1. Check whether there is enough working space on site, and the working surface should be flat and solid and not soft and collapsed.
2. If the working surface is uneven or the steel bar is flat, use 600*60*60MM wood planks to level up, and the solid square frame should be tightened and fixed with steel wire ropes and should not be tilted.
3. When placing the concrete placing boom vertically upwards, use the steel pipe of the shelf to make the space balance frame of the stabilizer. Use four oil wire ropes to tighten and insert the safety pins of the flower basket to prevent decoupling and fix it before the cloth construction can be carried out. (Note: Due to different construction site conditions, the factory does not provide rack steel pipes, oil wire ropes and tensioning devices)
4. Use shelf steel pipes at the elbows of the stand, and fix the elbows at the center of the square stand to prevent accidents caused by excessive impact.
5. Check whether sodium and calcium base grease is injected into each lubrication point.
1. The operator of the construction operation of the concrete placing machine must first read the operating manual of the concrete placing machine, and understand the relevant composition and safety factor of the manual placing machine in detail.
2. Strictly follow the relevant safety rules and do not lengthen and raise the concrete placing boom machine at will.
3. Before the concrete placing machine works, check whether the bolts are tight, whether the counterweight box and the boom are balanced, and whether the welding part of the placing machine has open welding or not.
4. Operators should establish safety awareness. Once abnormal equipment failures are found during operation, they should immediately shut down for inspection, and continue to work after the failure is rectified.
5. When the concrete placing boom machine is operating, it should be directed by a special person. Before walking, pay attention to whether there is any abnormality or failure on the track or in the operating range. It should be shut down immediately for inspection, and the work can be continued after troubleshooting.